Brownsburg Town Council Proposes 92 Million Dollar Lincolnwood Park Master Plan

0
2025 Lincolnwood Park Master Plan

April 24, 2025 – 

At A Glance:
The proposed Lincolnwood Park Master Plan contains a Multi-Purpose Indoor Rec Center, Outdoor Aquatics, Outdoor Amphitheater, Walking & Biking Trails and Paved Parking for 340 vehicles and additional items whose present day concurrent construction costs are estimated at 92+ million dollars.  The town council has yet to identify sources to completely fund the construction of the project.

A link has been provided   >> Click Here << and the public is encouraged to provide their input to the proposal.

Please check back, this article will be updated with additional details.

The Story Continues:
The 2025 proposal takes into account public comments received from two previous attempts (2017-2019 and 2021-2023) by the town to design a similar amenity.  The final 2024 design was met with “underwhelming” support by the community. The current attempt, incorporates a bigger outdoor component and devises a master plan for the entire site.

2025 Proposed Master Plan – Key Features

Outdoor Amphitheater – Lawn Seating 4,000 persons, Accessible seating for 500 Persons, 3,200 SF Covered Stage w/support spaces, multiple public restrooms located top and bottom. Entry Plaza with ticketing, Shaded Seating, and Food Truck Parking.

Outdoor Aquatics Center – 6,400 SF Leisure / Activity Pool w/zero-entry edge. Separate (4) Lane 25 yard lap pool. Separate Water Slides and Water play structure. Shaded shelters & Cabanas, Bath House, Concession area.

• Multi-Purpose Indoor Recreation Center – 2 levels
Upper Level – Main Public Entry, 2 Lane Running Track, Fitness Floor, Outdoor Terrace, (2) Group Exercise Rooms, Administration Spaces.

Lower Level – 2-Court Gymnasium, Indoor Aquatics (4) 25 yard lap pool, Lifestyle/Activity Pool, Current Channel.  Indoor Adventure Play, Party room, Locker rooms & Family Changing,  (3) General Program Rooms, Multi-Use room (sub-dividable). Maintenance / Support Areas.

Onetime vs Phased Construction:

If constructed all at once, today’s cost estimates are 92+ million dollars.  Using a 3 phase approach and today’s costs, the project can be broken out as:

$20.5 Million – Outdoor Aquatics
$55.0 Million – Multi-Purpose Indoor Recreation Center
$16.5 Million – Outdoor Amphitheater

No timelines have been established, and all associated costs are likely to increase over time.

Funding the construction:

No funding sources for the construction of any of the phases were provided during the presentation. 

Ongoing Operation Expenses:

The proposal recognized that facilities of this type perform at an operational deficit.  As the facility concepts are further developed, operating budgets will change. Separate operational budgets were presented one for Multi-purpose Indoor Recreation Center and another for the Outdoor Aquatics Facility. 


Additional information:

>> Click Here << Lincolnwood Park Feasibility Study Report

>> Click Here << Town Council April 24, 2025 Presentation

Click on the image below to goto the Lincolnwood Park Master Plan Comment Form

Click on the image to be taken to the Lincolnwood Park Master Plan Comment Form 

 


Click on the map for directions to Lincolnwood Park
Click on map for directions

Please check have you received an invite to “LIKE” the Brownsburg Sentinel ?
Click on image and LIKE our page!

Do you like our content?  Please help us Grow!Click on the LOGO above. GOTO Facebook and “LIKE” our Page! Thank You!


Content via:
The Editor
Town of Brownsburg
Google Maps